Kedungrong’s Power: Community Self-Reliance Runs This Micro Hydro Project

Kedungrong Hamlet, Kulon Progo, Yogyakarta, stands as a clear example of energy independence, operating outside centralized development models. Enter Nusantara Team spent three days, from Saturday, November 15 to November 17, 2025, documenting this community effort. We found that this Micro Hydro Power Plant doesn’t just provide light; it is the core system powering the residents’ self-management (swadaya) spirit and their local economy.

Starting Small, Growing Big

The Micro Hydro project began modestly. In 2004, a research project by Gadjah Mada University (UGM) installed a small Pico Hydro unit generating just 450 Watts, enough for streetlights for about 18 months.

The project grew significantly after coordination with the Ministry of Energy and Mineral Resources. Despite initial resident skepticism, visual presentations showcasing the full system (dam, pipeline, turbine) convinced the community. After securing permits up to the central government level, the independent MHP was built, scaling up power to 18 kW and 20 kW.

Run by the Community, Paid for by Javanese Calendar

The Micro Hydro sustainability is rooted in its local financing system. The residents manage the entire operation themselves (swadaya).

Operations are funded by a mandatory fee of IDR 12,000 per user household (KK). Crucially, they don’t pay monthly, but rather follow the Javanese calendar, every Selasa Kliwon, which averages about 10 payments per year. This fund covers all operational costs and maintenance.

The Daily Fight Against Trash

Keeping the power stable requires daily effort from the operators. Pak Rejo, a key figure, is a witness to this ongoing struggle.

Every day at 4 PM, the operator must clear debris and trash that clogs the water intake. This trash, often washing down from Temanggung upstream, is the Micro Hydro biggest threat. Clogs reduce the water flow, causing power output to drop or even the machine to shut down.

The Micro Hydro benefits are significant. When the national grid (PLN) fails during the rainy season, these homes never lose power. Furthermore, the much lower electricity cost directly supports small local businesses, including workshops, carpentry, welding, and laundries.

The Kedungrong Micro Hydro story demonstrates how grassroots initiative and self-reliance can be a highly effective model for renewable energy access in Indonesia. However, this local success, and the potential for thousands of other renewable energy projects, cannot continue to scale up without robust government support especially in financing large infrastructure needs and creating clear regulations that actively promote small-scale renewable energy. The community has done its part by creating the spark and the government must provide the resources for the fire to grow.